Installation methodology

"Engineering know-how for your most critical digital challenges."

The creation of an optical link between two racks is divided into 6 stages

Structured cabling procedure

1. Cable ducting (false floor or overhead)

Complies with wiring regulations and site constraints

  • Cable preparation
  • Cable routing
  • Stranded wire production
  • Cable tray mounting

2. Bay connections (outgoing & incoming)

  • Connection to drawers or front panels, with love 2 metres at each end
  • Fixing equipment in racks
  • Combing cables for neat organization

3. Conformity testing - ISO 11801-2 / ISO 14763-3 standards

  • Optical testing photometry and reflectometry on 100 % links
  • Double meaning & double wavelength
  • Submission of a measurement file certifying compliance with specifications

4. Labeling

  • Cables and drawers identified according to your bill of materials, with labels BRADY self-protected
  • Label application :
    • 30 cm from ends
    • every 10 linear metres
    • at every change of direction
    • 1.70 m on vertical surfaces
  • Instant readability without cable handling

5. Plans & diagrams (option)

  • Updating bay occupancy plans
  • Delivery of wiring diagrams to the customer

6. Final acceptance

  • Check volumes and product conformity
  • Validation of drawings & diagrams
  • Checking installation rules
  • Labeling control
  • Complete optical recipe : recipe books, calibration certificates, test & measurement reports