Installation methodology
"Engineering know-how for your most critical digital challenges."
The creation of an optical link between two racks is divided into 6 stages
Structured cabling procedure
1. Cable ducting (false floor or overhead)
Complies with wiring regulations and site constraints
- Cable preparation
- Cable routing
- Stranded wire production
- Cable tray mounting
2. Bay connections (outgoing & incoming)
- Connection to drawers or front panels, with love 2 metres at each end
- Fixing equipment in racks
- Combing cables for neat organization
3. Conformity testing - ISO 11801-2 / ISO 14763-3 standards
- Optical testing photometry and reflectometry on 100 % links
- Double meaning & double wavelength
- Submission of a measurement file certifying compliance with specifications
4. Labeling
- Cables and drawers identified according to your bill of materials, with labels BRADY self-protected
- Label application :
- 30 cm from ends
- every 10 linear metres
- at every change of direction
- 1.70 m on vertical surfaces
- Instant readability without cable handling
5. Plans & diagrams (option)
- Updating bay occupancy plans
- Delivery of wiring diagrams to the customer
6. Final acceptance
- Check volumes and product conformity
- Validation of drawings & diagrams
- Checking installation rules
- Labeling control
- Complete optical recipe : recipe books, calibration certificates, test & measurement reports
"They trust us

hoppen

acorus

impala

outscale

telehouse

equinix

otsi

elbow

ibrowse

criteo

sg

auntie

afpa

department

microsoft

sparkle

claranet

copalec